| 2/20/2025 | Measur+1Visit | |
| 8/23/2022 | Inspection Assessing | REV PROP FOR NBHD ANALYSIS- FORGOT TO ADD HEAT PUMP AND EXTRA PLUMB FEATURE DURING PREVIOUS VISIT- HAVE ADDED IT. |
| 3/30/2022 | Inspection Assessing | ADDED HOMESTEAD- UPDATED PHOTOS- ADDED HEAT PUMP- EXTRA PLUMB FEATURE FOR DBL BTHRM SINK- 16X24 WDK- CHANGED FSP TO BAS & FBM- EXTENDED FGR TO 16X24- ADDED 12X8 SHED |
| 8/28/2018 | FINAL | |
| 6/1/2018 | TOP OF PIPE | |
| 5/9/2018 | SUB GRADE | |
| 4/17/2018 | INSULATION INSPECTION | |
| 4/10/2018 | Elec Rough In | |
| 4/5/2018 | Framing | |
| 4/5/2018 | PLUMBING ROUGH IN | |
| 3/28/2018 | Listed | |
| 3/21/2018 | Electric Service | |
| 1/31/2018 | Foundation | |
| 10/10/2013 | Changed Lot Size | 119 SQFT WAS ADDED TO LOT PER DEED 16573/841. |
| 3/14/2008 | Changed Lot Size | .45 ACRES WAS ADDED TO THIS LOT FROM M23 L20. |
| 10/21/2006 | Changed Lot Size | PER SUBDIV PLUS ADDED LAND |