| 2/19/2025 | Measur+1Visit | |
| 2/7/2020 | Electric Finish | After the fact permit |
| 2/7/2020 | Measur+Listed | CHANGED TO PART OF BASEMENT FBM PER AFTER THE FACT PERMIT. |
| 1/17/2015 | Assessor Reviewed | |
| 9/21/2012 | Assessor Reviewed | WORK IN BASMENT NOT DONE ENOUGH TO VALUE, SOME DRYWALL ETC VERY PARTIAL |
| 10/21/2008 | Changed Lot Size | PER SUBDIV |
| 3/31/2008 | Final Miscellaneous | CO ISSUED BASEMENT TO REMAIN UNFINISHED UNTIL PROPER PERMITS ARE OBTAINED (ELEC) |
| 3/13/2008 | Measur+Listed | |
| 6/18/2007 | Elec Rough In | RECHECK ROUGH PASS |
| 6/11/2007 | Framing | |
| 6/11/2007 | Plumbing | |
| 4/13/2007 | Plumbing | SUB SLAB |
| 4/2/2007 | Changed Lot Size | ADJUSTED LOT SIZE PER NEW SURVEY. |
| 3/29/2007 | Measur+Listed | |
| 3/5/2007 | Electric Service | DO NOT CALL IN TO CMP TILL WE ARE ABLE VERIFY PICTURES OF UNDERGROUND |
| 1/24/2007 | Foundation | |