Visit History
| 11/8/2024 | Measur+Listed | |
| 4/2/2024 | Inspection Assessing | 4/1 INSPECTION. ADDED ADDITION IN SECTION 2. PUT AT 25% UC |
| 3/16/2020 | Measur+Listed | TAKEN OUT OF UC PER CODE. |
| 2/11/2020 | FINAL | |
| 11/25/2019 | PLUMBING ROUGH IN | Above Slab |
| 11/4/2019 | Framing | |
| 10/22/2019 | Framing | |
| 10/9/2019 | Foundation | Rebar |
| 8/26/2019 | Plumbing | Final underground plumbing |
| 8/16/2019 | PLUMBING ROUGH IN | Underground |
| 8/12/2019 | PLUMBING ROUGH IN | Partial underground plumbing |
| 7/31/2019 | Foundation | |
| 7/30/2019 | Foundation | |
| 7/29/2019 | Foundation | |
| 7/26/2019 | Electric Service | conduit |
| 7/25/2019 | Foundation | Footings and pour |
| 7/24/2019 | Foundation | Footing and pour |
| 7/22/2019 | Foundation | Footing and pour |
| 7/18/2019 | Foundation | Footings |
| 7/15/2019 | Foundation | footing |
| 7/11/2019 | Foundation | footing |
| 7/10/2019 | Foundation | |
| 7/9/2019 | Foundation | Footing |
| 6/27/2019 | Electric Service | Temp |