Visit History
| 2/11/2025 | Measur+1Visit | |
| 1/30/2023 | Inspection Assessing | ADDED 5% FUNCTIONAL DEP FOR STRUCTURAL ROOF ISSUES. REDUCED LAND VALUE BY 10% FOR SHARED DRIVEWAY |
| 9/16/2022 | Change Reinspection Rereview | REVIEWED BUILD PLANS- ADJUSTED THE FOLLOWING PER BUILD PLANS: FGR WENT FROM 592-SQFT TO 578-SQFT, BAS/UBM WENT FROM 2362-SQFT TO 2376-SQFT, ADDED CA1 352-SQFT, ADDED 1 EXTRA PLUMB FEAT FOR DBL SINK, PER AERIAL PHOTO ADDED PTO 520-SQFT |
| 2/8/2022 | Assessor Reviewed | INCORRECT STYLE REVIEWED PLANS AND RE SKETCHED BUILDING TO CORRECT ERRORS CHANGED STYLE FROM COLONIAL TO RANCH |
| 3/29/2017 | Listed NOH | |
| 10/13/2016 | Change Legal Ownership Change | |
| 7/20/2016 | FINAL | |
| 6/25/2016 | Listed | OWNER IS WORKING ON SITE; 1ST FLR = RADIANT HEAT; 2ND FLR IS PROPANE / FHW; GOOD TRIM (POPLAR); CROWN MOLDINGS; CUSTOM TILE M/BATH. FOUNDATION ONLY 4/1/16. |
| 5/18/2016 | Electric Service | |
| 5/13/2016 | INSULATION INSPECTION | |
| 5/10/2016 | Framing | |
| 5/10/2016 | PLUMBING ROUGH IN | |
| 5/6/2016 | Elec Rough In | |
| 3/28/2016 | Listed | TOOK PHOTO |
| 3/17/2016 | Electric Service | |
| 3/14/2016 | Foundation | |
| 5/1/2013 | New Lot Created | THIS LOT WAS CREATED PER APPROVED SUBDIV PLAN SIGNED 2-12-2013. |