Visit History
| 6/26/2025 | Measur+1Visit | |
| 8/22/2022 | Inspection Assessing | REV PROP FOR ASSESSMENT DISCREPANCIES AMONG THE CONDOS- REWORKED SKECTH TO BETTER REFLECT BUILDING PLANS- ADD GAS FP- ADJUSTED CONSTRUCTION DETAILS: HARDWOOD/TILE, HOT WATER HEAT- NO HEAT PUMP-UST TO FST |
| 7/8/2019 | Measur+Listed | COMPLETE |
| 4/30/2018 | Card Prepped | 73% COMPLETE 0N 04/01/2018 |
| 3/30/2018 | Listed NOH | |
| 12/15/2017 | Elec Rough In | |
| 12/15/2017 | Framing | |
| 12/8/2017 | Electric Service | |
| 11/17/2017 | PLUMBING ROUGH IN | |
| 9/20/2017 | Card Prepped | CONDOS AT DUROSS PLACE _ 8 UNITS |
| 9/18/2017 | PLUMBING SUB SLAB | |
| 9/15/2017 | Foundation | |