| 9/30/2025 | Measur/Inf/Dr Info taken at door. | |
| 3/27/2025 | Measur+1Visit | |
| 2/22/2022 | Change Legal Ownership Change | NEW OWNER UPDATE- PER ONLINE PHOTOS- CHANGED FBM TO SFB |
| 10/27/2021 | Inspection Assessing | OC INSPECTION FOR FINISHED BASEMENT- HOMEOWNER STATED ROOM IN BASEMENT IS A BEDROOM- UP TO CODE- CHANGED BEDROOM COUNT FROM 3 TO 4 |
| 9/30/2020 | Card Prepped | UC FOR FINISHED BASEMENT AND HEAT PUMP. |
| 4/1/2020 | Measur+Listed | |
| 12/13/2019 | FINAL | |
| 10/28/2019 | INSULATION INSPECTION | |
| 10/23/2019 | PLUMBING ROUGH IN | |
| 10/23/2019 | Elec Rough In | |
| 10/23/2019 | Framing | |
| 8/19/2019 | Foundation | |
| 3/21/2019 | New Lot Created | LOT NUMBER 26 ON SETTLERS LANDING PHASE II |