Visit History
| 8/1/2025 | HEARING NO CHANGE | |
| 3/5/2025 | Assessor Reviewed | |
| 11/15/2024 | Measur+Listed | |
| 7/15/2019 | Electric Finish | Final follow up |
| 6/21/2019 | Electric Finish | Follow up final |
| 6/20/2019 | Electric Finish | Fire alarm |
| 6/19/2019 | FINAL | |
| 5/30/2019 | Plumbing | Sprinkler system test |
| 4/30/2019 | Foundation | Rebar |
| 4/26/2019 | Foundation | rebar |
| 4/24/2019 | Framing | rough framing of mezzanine and office ceiling inspection |
| 4/5/2019 | Foundation | Mesh inspection in mezzanine |
| 4/5/2019 | Electric Service | |
| 4/3/2019 | Foundation | Concrete inspection |
| 4/1/2019 | Foundation | Rebar |
| 4/1/2019 | Measu/LtrSnt Letter Sent no response | |
| 3/29/2019 | Foundation | Rebar for footers on transformer and monument sign |
| 3/28/2019 | Foundation | rebar on handicapped ramp and stairs |
| 3/27/2019 | Card Prepped | CARD PREPPED_NEED TO PICK UP PARKING LOT_ANY OUTBUILDING VALUE |
| 3/26/2019 | Foundation | Rebar |
| 3/25/2019 | Foundation | Rebar footers |
| 3/25/2019 | New Lot Created | PORTION OF 072-002-000-000_SEE 072-002-000-000 FOR BUILDING PERMIT RECORDS |
| 3/22/2019 | Foundation | Rebar |
| 3/18/2019 | Foundation | Rebar |
| 3/8/2019 | Elec Rough In | |
| 3/7/2019 | PLUMBING ROUGH IN | |
| 3/1/2019 | Framing | |
| 2/22/2019 | PLUMBING SUB SLAB | |
| 2/15/2019 | Foundation | Rebar |
| 2/1/2019 | Foundation | Pre-concrete |
| 1/24/2019 | Foundation | Rebar |
| 1/7/2019 | Foundation | |
| 12/27/2018 | Elec Rough In | |
| 12/20/2018 | PLUMBING SUB SLAB | |
| 12/18/2018 | PLUMBING SUB SLAB | |
| 12/17/2018 | PLUMBING SUB SLAB | |
| 10/31/2018 | Foundation | |
| 2/8/2017 | Foundation | Pre-pour insp |