Visit History
| 2/28/2025 | Assessor Reviewed | |
| 11/6/2024 | Measur+1Visit | |
| 3/31/2022 | Assessor Reviewed | ADJUSTED CONDITION FACTOR DOWN TO .75 |
| 12/18/2018 | FINAL | theater seating |
| 12/12/2018 | Framing | |
| 12/12/2018 | Elec Rough In | |
| 12/11/2018 | Framing | |
| 12/11/2018 | Elec Rough In | |
| 12/10/2018 | Framing | |
| 12/10/2018 | Elec Rough In | |
| 11/29/2018 | Framing | |
| 11/29/2018 | Elec Rough In | |
| 11/20/2018 | Framing | |
| 11/20/2018 | Elec Rough In | |
| 11/13/2018 | Elec Rough In | new chairs |
| 6/27/2018 | FINAL | |
| 6/27/2018 | Electric Finish | |
| 6/4/2018 | Framing | OTTO PIZZA |
| 6/3/2010 | Relisted | |
| 8/20/2009 | Changed Lot Size | PER DEED BK 15622 PG 0109, A 15FT X 222 FT STRIP OF LAND WAS GIVEN TO STATE OF MAINE DOT BY ZYACORP FOR THE PURPOSE OF WIDENING THE ROAD/US ROUTE 1. |
| 6/30/2009 | Assessor Reviewed | ADDED IMAX PLUS NEW LOBBY AND REST |
| 4/28/2009 | Final Miscellaneous | FINAL INSPECTION PASSED |
| 3/27/2009 | Plumbing | SUB SLAB BISTRO |
| 3/20/2009 | Plumbing | ROUGH INSPECTION OF MANIFOLD AND BOTH SMALL BATHROOMS JUST OUTSIDE IMAX ENTRY DOORS. |
| 3/12/2009 | Plumbing | SUB SLAB KITCHEN |
| 3/11/2009 | Plumbing | SUBSLAB KITCHEN GREASE TRAPS |
| 3/10/2009 | Framing | I-MAX WALLS |
| 3/9/2009 | Plumbing | ROOF DRAIN |
| 2/25/2009 | Plumbing | ROOF DRAINS OVER BISTRO |
| 1/30/2009 | Changed Lot Size | ADDED 4.38 ACRES WHICH WAS CONVEYED TO THIS LOT FROM LOT 4. |
| 12/18/2008 | Plumbing | SUBSLAB ( ROOF DRAIN) |
| 12/4/2008 | Foundation | IMAX SIDE, SCREEN WALL FOUNDATION AND REBAR INSPECTION |
| 12/3/2008 | Foundation | UPPER WALLS BEFORE BACKFILL IMAX SIDE |
| 12/2/2008 | Foundation | NORTH (IMAX) SIDE FOUNDATION REBAR ON LOBBY SIDE OF THEATER. ALSO CHECKED FOOTING ON SCREEN SIDE AND REBAR ON FOUNDATION WALL, EXTERIOR SIDE. REBAR BONDED TO GROUNDING WIRE ON THIS SIDE. |
| 12/1/2008 | Foundation | FOUNDATION WALL AFTER CONCRETE POUR, WEST AND SOUTH WALLS, BISTRO SIDE |
| 11/30/2008 | Foundation | REBAR IN FOUNDATION WALLS, WEST AND SOUTH SIDE OF BISTRO WING. CHANGED TO #4 REBAR PER OK WITH FOUNDATION ENGINEER MACLEOD |