Visit History
| 8/7/2025 | HEARING NO CHANGE | |
| 11/5/2024 | Measur+Listed | |
| 8/13/2018 | Final Miscellaneous | |
| 8/13/2018 | FINAL | |
| 5/9/2018 | INSULATION INSPECTION | |
| 5/7/2018 | Elec Rough In | |
| 4/19/2018 | PLUMBING ROUGH IN | |
| 4/11/2018 | Framing | |
| 4/4/2018 | Foundation | |
| 1/3/2018 | Listed | |
| 1/3/2018 | FINAL | BATHHOUSE |
| 11/2/2017 | Elec Rough In | BATHHOUSE |
| 11/1/2017 | PLUMBING ROUGH IN | BATHHOUSE |
| 10/26/2017 | Framing | BATHHOUSE |
| 9/22/2017 | PLUMBING SUB SLAB | BATHHOUSE |
| 5/10/2017 | PLUMBING SUB SLAB | SPLASH PAD |
| 6/8/2015 | Assessor Reviewed | REMOVED PROP FROM TG - SEE ASSOCIATED DOC |
| 5/20/2015 | PLUMBING ROUGH IN | LAUNDRY/BATH HOUSE |
| 4/30/2015 | Elec Rough In | LAUNDRY/BATH HOUSE |
| 4/27/2015 | Elec Rough In | PANCAKE HOUSE |
| 4/27/2015 | Framing | PANCAKE HOUSE |
| 4/22/2015 | PLUMBING ROUGH IN | PANCAKE HOUSE |
| 4/16/2015 | Electric Service | MAINTENANCE BUILDING |
| 4/7/2015 | Elec Rough In | OFFICE |
| 3/12/2015 | Foundation | EQUIPMENT GARAGE |
| 9/17/2009 | Electric Service | FROM PANEL BOARD TO THREE CAMPSITES AND TWO STUBS FOR FUTURE |
| 9/16/2009 | Electric Service | FROM NEW PAD TO PANEL BOARD |
| 9/15/2009 | Electric Service | TRENCH FROM NEW POLE TO NEW PAD |
| 5/21/2007 | Electric Service | |
| 10/19/2006 | Electric Finish | |
| 9/28/2004 | Hearings | 9-28-04 HEARING N/C |