Visit History
| 6/27/2025 | Measure - Info Card left | 5:28 |
| 6/26/2025 | Measur+1Visit | |
| 8/26/2019 | FINAL | Siding |
| 5/10/2019 | FINAL | Addition |
| 3/21/2019 | Measu/LtrSnt Letter Sent no response | |
| 8/31/2018 | INSULATION INSPECTION | |
| 8/17/2018 | PLUMBING ROUGH IN | |
| 8/15/2018 | Elec Rough In | |
| 8/13/2018 | Framing | |
| 7/9/2018 | Foundation | |
| 4/9/2011 | Listed | INFO FROM OWNER - BATH & KITCHEN REHAB |
| 8/11/2010 | FINAL | KITCHEN AND BATH RENOVATIONS AND STRUCTURAL SHORING |
| 6/29/2010 | Complete Rough In | PLUMBING FOR FIRST FLOOR BATHROOM SOME CODE VIOLATIONS ON OLD PLUMBING WILL BE ADDRESSED IN PHASE 2 OF PROJECT |
| 11/23/2009 | Final Miscellaneous | REPLACEMENT WINDOWS |
| 1/7/2008 | Listed NOH | SAME INFO |
| 4/30/2004 | Measur+1Visit | 08-18-04 HEARING - NC PER DHS |
| 12/9/2002 | Listed NOH | |